You need to login before you can view or download document
ELECTRICAL FAULT LEVEL REDUCTION AT FARLEIGH MILL
By REG MILLETT
THIS PAPER discusses the implications of electrical plant growth within
established sugar mills and the resulting adverse impact on the safety of
operating and maintenance personnel. This case study follows the
amalgamation of a number of Mackay Sugar Mills to form the Mackay
Sugar Co-operative Association Ltd. With the rationalisation of the mills,
plant from closed factories was relocated to the other mills. As part of this
process the 5 MW alternator from Cattle Creek Sugar Mill was installed
at Farleigh Mill. This increased the site-based generation from 8 MW to
13 MW, which is a 62.5% increase in capacity. As was discovered about
10 years later, this increased the electrical fault level above the equipment
rating for some of the existing installed electrical plant, including the 3.3
kV switchgear. Over the last 10 years we have been through several
processes, including fault studies, risk assessments, implementation of
temporary control measures, design of a system to fix the situation, and
the capital works to fix the problem. Following the capital works we have
reassessed some of the switchboards that were highlighted as requiring
replacement and the new analysis has shown that there is no longer a need
to replace these switchboards as the fault levels are now back within
acceptable limits. The whole process identifies the need to preform plant
fault studies prior to implementing any major electrical plant expansions.